Construction Contracts: Three Signatures Between Yes and the First Day on Site

The homeowner says yes on a Thursday. By Monday you are pricing lumber, calling the excavator, and holding a framing crew for a start date nobody has written down.

That gap between the yes and the paperwork is where most of the trouble I see in residential building starts. There is a signed bid, or a handshake, or an email that says "let's do it." There is not yet a document that says what "it" is, what it costs, when money moves, and what happens when the ground turns out to be ledge.

Most builders I talk to have one contract. It was written years ago, somebody's attorney looked at it once, and the last client's name is still in the header of the Word file. It gets used for a kitchen and for a two-million-dollar house on the water, and it is two pages long in both cases.

This post is about the construction contracts that belong in that gap, in the order they get signed, and what the last one has to say.

Construction contracts come in a sequence

A custom home does not get one signature. It gets three, and each one buys a different thing.

Before any of them there is the preliminary estimate, which nobody signs. It is a planning number with a range around it, the items it leaves out, and a date it expires. I wrote about why it has no signature line in estimate, bid, quote, proposal. It settles whether the conversation should continue. It does not commit anyone to anything, and it should be impossible to mistake for a price.

Then the money starts moving, one document at a time.

The letter of intent. The owner has said yes in principle. Nothing is drawn to permit level, nothing is priced to the stud, and you are about to spend weeks on budget development, sub coordination and vendor pricing. The letter of intent takes a retainer for that work and holds your calendar for their job. The budget inside it is labeled as a planning number, in writing, so it cannot be quoted back to you as a price in the spring. I cover this one on its own in the construction letter of intent.

The pre-construction design agreement. This one pays for the design work. The fee comes back off the build if they build with you, which makes it the easiest of the three to sign. And the drawings stay yours until the fee is paid, which is what keeps a set from being carried to another builder to price.

The construction agreement. The one people mean when they say "the contract." It sets the contract sum and replaces everything signed before it.

Each document should name the one that comes next and say what it replaces. An owner holding the letter of intent should know the design agreement is coming. An owner holding the build contract should know it supersedes the other two. When every page carries the same stage marker, nobody is confused about which paper they are holding.

Types of construction contracts

Before you write the build agreement you have to decide how the price works. There are four common shapes in residential work, and each one moves risk to a different side of the table.

Fixed price, also called lump sum. One number for a defined scope. If the framing runs over, that is yours. If you bought well, that is also yours. It only works when the drawings are complete enough to count from, because every assumption in the take-off is now a promise.

Cost-plus. The owner pays what the work actually costs, plus your fee, with the books open. The risk on quantities sits with the owner. The risk on trust sits with you, because an open-book job lives or dies on how clean the books are.

Guaranteed maximum price. Cost-plus with a ceiling. Costs are passed through up to a stated maximum, and anything above it is yours. Owners like the ceiling. Builders need the drawings to be far enough along that the ceiling is a number they can actually stand behind.

Time and materials. Hourly labor plus materials at cost or marked up. It fits small, undefined work, like repairs and investigative demo. On a whole house it tends to make everyone nervous, because nobody knows the end number until the end.

None of these is the right answer everywhere. The honest version of the choice depends on how complete the drawings are, how much of the site you can see, and how much the owner wants certainty versus transparency. I set the two most common side by side in cost-plus vs. fixed price.

What the construction agreement has to carry

The two-page contract usually has a scope paragraph, a price, a start date, and a signature block. Here is what it leaves out, and what a real one carries.

The contract documents, named by date. Which drawing set, which specification, which selections schedule, each with its revision date. When the owner says "that's not what we agreed," the answer is on page one. Without it, you are arguing about memory.

A draw schedule that adds up. Milestones tied to work in place, each with a dollar figure, totaling the contract sum exactly. This sounds too obvious to mention. It is the defect I find most often in builders' paperwork. The specimen on our document suite page shows a fictional job where the milestones total $735,200 against a contract sum of $746,800, an $11,600 gap nobody notices until the last draw. How to lay one out is in the construction draw schedule.

Allowances carried as allowances. The tile, the fixtures, the appliances the owner has not picked yet. Each one needs its own line, its own dollar figure, and a stated rule for what happens when the selection comes in over or under. Buried inside a lump sum, an allowance turns into a fight about what was "included."

Written change orders before changed work. The rule is simple to write and hard to keep: no changed work proceeds until a change order describing it, pricing it, and adjusting the schedule is signed. That covers concealed conditions too. When you open a wall and find rot, the fix is priced and signed before it is built, not invoiced after. I laid out the form itself in the change order template.

Warranty. What you warrant, for how long, what voids it, and how a claim gets made. Leave this out and you will have the conversation for the first time in year two, with a homeowner who has already decided what the answer should be. How warranty requests get handled once the keys change hands is in construction closeout.

Insurance and permits. Who carries what coverage, at what limits, and who pulls and pays for which permits. State it, even when it feels like everyone knows.

Termination and disputes. How either side gets out, what is owed when they do, and where a disagreement goes before it goes to court. Mediation, arbitration, venue. It is the section nobody reads at signing, so write it plainly.

Statutory notices. Every state has its own required language. Registration and license numbers, cancellation rights for certain contracts, lien notices, required warnings. These differ state by state, and they are the part of the contract that should come from your attorney, written once for your state, and printed on every job after that.

Run your own contract past an attorney in your state; this post is not legal advice. What I can say is which sections are missing when a contract comes across my desk, and the list above is the list.

How to write a construction contract that holds up

The drafting advice I give builders is mostly about process, because the clauses are well known. The failures come from how the document gets produced.

Start from a locked template, not the last job. Copying last year's contract and editing it forward is how the previous client's name ends up in section four. Structure should stay fixed from job to job. Only the job-specific facts should change.

Separate the facts from the form. The owner, the address, the contract sum, the draw milestones, the allowance figures, the drawing dates. Put them in one place, fill them in once, and let the document carry them into every section. When the sum changes, it changes everywhere.

Check the math before it prints. The draw schedule totals the contract sum. The allowances match the allowance schedule. The deposit matches the first draw. These are arithmetic, and they fail because nobody runs the addition on a document they think of as legal text.

Refuse to print the blanks. A statutory block left empty, a warranty section deleted to save a page, a placeholder still sitting in square brackets. A contract that goes out with any of these has a defect the owner can see and you cannot.

Make it look like the proposal that won the job. The owner chose you off a packet with your brand on it. If the contract that follows looks like a different company wrote it, the confidence you built during the bid leaks out at the moment it matters most. This is the same point I made about the proposal template: the reader judges the company by the paper.

What the suite refuses to print

The document suite in the Bid Room is built on exactly those rules. One template per document, structure locked in code, your brand in one file, the job's facts in another. The three documents are on the suite page with specimen pages from a fictional project.

What makes it useful is what it refuses to do. It will not write a PDF where the draw schedule misses the contract sum; it prints the gap instead. It will not quietly leave out a warranty; it flags the missing section. It will not invent statutory language for your state or drop it without saying so; it prints a visible reminder where your attorney's block belongs. And it lists back any placeholder still unfilled before the document goes to a client.

Every document carries the same line: templates, not legal advice, reviewed with your attorney before first use.

In the 785-contractor study, 95.8% showed no client-facing proposal system or portal on their website. The paperwork after the yes is usually in the same state as the paperwork before it: a file on somebody's desktop, copied forward one job at a time. That is where to start if the build side of your year feels like it runs on memory, and it slots into the marketing plan as part of the Systems layer, before anything that brings in more work.

Send the contract you use now

If you want to see where yours stands, send it, with the client's name blacked out or not. What comes back is that same job rebuilt as all three documents under your logo, and a marked-up list of every section above that yours skips. No charge and no call. The upload form sits at the foot of the document suite.

If you want the whole front end of the sale built, the proposal, the room, and the documents behind it, the published pricing is on the Bid Room rate card.

Book a working session