The Change Order Template That Keeps Draw Five Quiet
The framer opens a wall and finds rot in the sill plate. He tells the site lead. The site lead calls the owner, who says fix it. Everybody agrees on the phone, the work gets done that week, and the cost shows up on the next invoice as a line nobody remembers approving.
Six weeks later that line is the only thing the owner wants to talk about.
Nobody in that story did anything dishonest. The rot was real, the fix was right, and the owner said yes. What was missing was a piece of paper with a number on it and two signatures, dated before the saw came out. That piece of paper is a change order, and most of the arguments I hear about on residential jobs trace back to one that was never written.
What a change order is in construction
A change order is a written amendment to the construction agreement. It changes the scope, the contract sum, the schedule, or some combination of the three, and it becomes part of the contract the moment both sides sign it.
That last part is the whole point. The contract you signed named a drawing set, a specification, and a price. Anything that moves away from those documents is, legally and practically, a new agreement about a piece of the job. A text message saying "go ahead" is evidence that a conversation happened. It is a weak record of what was agreed, what it cost, and how many days it added.
So the rule in a well-built contract is short: changed work is written and signed before it is built. The construction agreement in the Bid Room document suite says it in those terms, concealed conditions included. The form below is how you live up to it on a Tuesday when the framer is standing there waiting.
Have your attorney read your own form before you rely on it; I am not one. What follows is what I have seen hold up on jobs and what I have seen fall apart.
The construction change order form, field by field
A change order template does not need to be long. It needs to be complete. One page is usually enough if every one of these is on it.
| Field | What goes in it | Why it is there |
|---|---|---|
| Change order number | Sequential, never reused | So "CO 7" means one thing to everyone |
| Contract reference | The agreement, and the drawing set and spec by date | Ties the change to a specific baseline |
| Description | What is being added, removed, or substituted, in plain words | The owner has to be able to read it without you in the room |
| Reason | Owner request, concealed condition, allowance reconciliation, or code / inspector requirement | Tells you later why the job moved |
| Price | The add or the credit, as a dollar figure | A change with no number is not a change order |
| Schedule impact | Days added or removed, even when the answer is zero | The completion date is part of the contract too |
| Revised contract sum | Previous sum, this change, new sum | Keeps a running total nobody has to reconstruct |
| Revised completion date | Carried forward the same way | Same reason |
| Signatures and dates | Builder and owner, both dated | The date proves it came before the work |
Two fields get skipped more than the rest.
The reason line feels like paperwork until the end of the job, when the owner says the house went over budget and you need to show that eleven of the fourteen changes were their own requests. Sorted by reason, the log answers that in a minute.
The schedule impact line gets skipped because the builder does not want to argue about days on a small change. Write zero if it is zero. Write three if it is three. A string of unrecorded small delays is how a completion date slides a month with no document explaining where the month went. The schedule those days come off of is in the construction schedule template.
Change order request vs. change order
These get used as if they were the same document. They are two steps.
A change order request is the question. The owner asks for something, or the site turns something up, and one side puts it in writing: here is what we want to change, please price it. Nothing is agreed yet. No work should start.
The change order is the answer both sides signed. It carries the price, the days, and the new contract sum. Once it is signed, the work can proceed.
Keeping them separate protects you in both directions. An owner who asks for a price has not committed to paying it, and you have not committed to doing the work until the number is accepted. When the two collapse into one conversation, you end up building on a request and billing on an assumption.
Some builders run the request through email and only formalize the signed change order. That can work. What does not work is skipping the second step because the first one felt like agreement.
Concealed conditions get priced before, not invoiced after
Back to the rot in the sill plate.
Concealed conditions are the hardest case because the work often cannot wait. The wall is open, the crew is there, and stopping costs money too. The temptation is to fix it and sort out the paper later.
The version that holds up is: stop the affected work, document what you found with photos, price the fix, and get the change order signed before proceeding. On a small repair that can happen the same day. The owner signs on a phone, the photo is attached, the price is on the page, and the framer goes back to work an hour later.
If the contract has a concealed-conditions clause, it should say exactly this: conditions that could not reasonably have been seen are priced and signed before the work goes on. The invoice then carries a change order number instead of a surprise.
Allowances get reconciled by change order
An allowance is a placeholder in the contract sum for something not yet selected: tile, fixtures, lighting, appliances. The contract should carry each one as an allowance, with its dollar figure, on its own page. I made the case for that page in you did not lose on price.
When the owner makes the selection, the difference between the allowance and the actual cost is a change order. Over the allowance, it is an add. Under, it is a credit. Either way it gets written, priced, and signed, and the contract sum moves.
This is where a lot of end-of-job friction comes from. The owner picked the tile eight months ago, it came in over, nobody wrote it up, and the overage lands in the final invoice. Reconcile each allowance by change order at the moment of selection. The owner sees the effect on the total while they can still pick a different tile.
The draw schedule has to move with it
A signed change order moves the contract sum. The draw schedule was built to add up to the original contract sum. If the change orders move the sum and the draw schedule does not move with them, the payments stop adding up to what is owed.
This sounds like a bookkeeping detail until final payment, when your balance and the owner's balance come out different. Decide in the contract how approved changes get paid: added to the next draw, spread across the remaining draws, or billed on their own when complete. Then keep a revised schedule of values that ties to the revised contract sum. I go through building one that adds up in the construction draw schedule.
On a financed job this matters twice, because the lender's draw process runs against a budget it approved. A change the bank never saw can leave a gap between what you are owed and what the bank will release.
Pricing the change
I am not going to print a markup figure here. What you carry on changed work is set by your costs and your contract. The rule that matters is that the contract says how changes are priced before the first one comes up, so the first change order is not also the first negotiation over your margin.
State in the agreement whether changes are priced as a fixed figure per change or at cost plus a stated fee. Then price every change the same way. An owner who can predict how a change will be priced argues far less about the price.
Where the template fits
A change order form works only if the contract above it is set up for it. The construction agreement has to name the drawing set and spec by date, carry allowances as allowances, say that changed work is written first, and include a draw schedule that totals the contract sum. Without those, the form has no baseline to change. The construction contracts post lays out the whole agreement and the two documents that come before it.
In the Bid Room suite, the construction agreement is document 03, generated in the builder's brand from a locked template, with the change-order clause built in. The generator refuses to print a draw schedule that does not total the contract sum. The rate card is on the Bid Room page. For where contracts fall in the order a builder should build things, see the marketing plan.